Better Cooling Choices — Cheaper, Too
Conventional wisdom often tends to lead
owners, contractors, and designers down the
same path when it comes to HVAC system
design. Many owners still believe that they
must spend more in first costs to achieve
higher efficiency and superior HVAC system
results. But rather than focus on the individual
pieces of HVAC equipment — and the price
tag that comes with each component — there
are often significant benefits to building
owners and occupants when engineers explore
an overall systematic approach to HVAC
design. An initial investment of time in the
early stages of design, along with the
application of a few basic fundamentals, can
yield superior HVAC systems at a lower
overall first cost — without sacrificing
quality.
In addition to lowering first costs, other
advantages of a holistic, systematic approach
include improved energy efficiency, lower
operating and life-cycle costs, smaller
equipment rooms, superior acoustics and
reduced environmental impact.
For a systematic approach to be successful,
consistent design criteria should be
established for the project. The criteria should
apply equally to all systems considered as
well the individual components, and should
include indoor and outdoor space temperature
and humidity conditions for summer and
winter seasons, total cooling and heating
loads, noise criteria, building skin loads,
interior lighting and equipment loads, outside
air ventilation loads, coil face velocities and
ductwork velocities.
Many of the fundamental issues and
assumptions that come into play may seem
like common sense. But given the number and
type of relatively inefficient HVAC systems
installed every year, one can see how often
these fundamentals are not applied. If properly
considered within the overall context of the
building design, each of these fundamentals
should help reduce cost and improve
efficiency.
Here are some basic principles to consider:
Physically smaller HVAC equipment requires
less overall space and improves core
efficiencies as compared to larger HVAC
equipment.
Moving less air results in lower fan
horsepower, less sound attenuation, smaller
equipment and smaller ductwork.
Quieter HVAC equipment requires less sound
attenuation and minimizes special
architectural room construction when
compared to nosier HVAC equipment.
Moving less water will result in smaller piping
systems, smaller pumps, and lower pump
horsepower. Smaller pump motors, smaller
fan motors, and lower refrigeration
horsepower require smaller electrical systems
and use less energy.
Concentrating the major electrical loads such
as large motors and refrigeration equipment
near the electrical utility service entrance is
usually less expensive than locating large
electrical loads at a greater distance from the
electrical service entrance.
Using fewer materials and smaller equipment
minimizes environmental impact.
The following case studies reflect a systematic
approach to design — in each case yielding
lower first costs for the building owners.
These examples are typically larger in size —
more than 200,000 square feet — and are
based on chilled water systems versus self-contained
packaged water-cooled systems.
(Many contractors and designers believe that
self-contained packaged water-cooled air
conditioning systems are less expensive than
chilled water-based systems. But a systematic
approach often proves otherwise.) These
projects each feature floor-by-floor variable
air volume (VAV) air distribution systems.
Cases in Point
Two Freedom Square:
Boston Properties, the owner and developer of
this 450,000-square-foot high-rise in Reston,
Va., opted to purchase custom air handling
unit equipment in lieu of standard, off-the-shelf
equipment. The custom units were more
expensive. However, the systematic approach
considered the architectural room
construction, ductwork sound attenuation,
wall construction, insulation systems, size of
the equipment room, optimization of fan
selections, variable speed drive size, and
electrical service size, among other aspects.
Although the custom equipment was more
expensive, the combined cost savings in other
areas, especially room construction and sound
attenuation, resulted in lower first cost.
The Tower Building:
The Tower Companies — owner and
developer of the new Tower Building along a
major thoroughfare in Montgomery County,
Maryland — selected a low-temperature
chilled water system in lieu of a packaged
water-cooled self-contained system. The
company’s primary motivation was to provide
a higher quality, more energy-efficient HVAC
system. But an analysis revealed there were
also first-cost advantages. Because of the size
of the floor plate —approximately 28,000
square feet — only one low-temperature
chilled water system was needed per floor.
The water-cooled packaged option required
two units per floor, which would have meant
two outside air risers, two sets of water risers,
two sets of power risers, more controls, more
sound attenuation, etc. Two units per floor
would have also required more than 250
additional square feet per floor—adversely
affecting core efficiency.
Hunters Branch:
Hunters Branch, a 350,000-square-foot high-rise
complex in Vienna, Va., provides a clear
example of how the electrical power
distribution system can play a pivotal role in
the HVAC system selection. Initial design
discussions with the owner and developer
team, Northwestern Mutual Life and The Orr
Company, addressed both chilled water and
packaged systems. By including the cost
savings found in the electrical power
distribution system, however, the first-cost
advantage swung toward the more efficient
chilled water system. The project’s 1,000-ton
chilled water central plant required
approximately 1,900 square feet and
positioned the major electrical loads
associated with the air conditioning system
within 50 feet of the main switchboards.
The chilled water system also resulted in a
reduction in switchboard size and overall
service entrance of approximately 3 to 4 watts
per square foot for the entire building — a
significant reduction in overall electrical
system capacity. Lower operating cost was a
benefit for choosing the chilled water system.
Tysons Two:
The Tysons Two project, a 350,000-square-foot
high-rise at Tysons Corner, Va., provides
an example of how optimizing the chilled
water and condenser water systems reduces
first costs and improves energy efficiency.
The chilled water differential temperature was
increased from the ARI standard of 10 to 18
degrees. This translated to a 45 percent
reduction in chilled water flow, smaller
pumps, lower pumping horsepower, smaller
piping sizes, smaller electrical service and less
insulation. The condenser water differential
temperature was increased from the ARI
standard of 10 to 15 degrees, which meant a
34 percent reduction in condenser water flow,
smaller pumps, lower pumping horsepower,
smaller piping sizes and smaller electrical
service. The cooling tower motor horsepower
remained the same.
It cost more up front to maintain the chiller
efficiency at the wider differential
temperatures. However, the additional cost of
the chillers was offset by the combined lower
cost of the pumps, electrical service to the
pumps, piping systems and other system
effects. If the owner, Lerner Enterprises, and
the design team had simply compared the cost
of chillers at the various differential
temperatures, a different conclusion would
have been reached.
USA Today/Gannett World Headquarters:
Given the size of the interior loads in this
800,000-square-foot project near Tysons
Corner, Va., as well as the limits on the
number of air handling unit rooms per floor
and the pressure to achieve acceptable noise
criteria levels directly outside of the air
handling unit rooms, this new headquarters is
a good example of how lowering the supply
air temperature and preconditioning the
outside air can solve a number of design
challenges while reducing first costs.
Given the design criteria, conventional 55-
degree supply air was not an option for
Gannett, which developed the project with
Hines. First, to solve the typical floor air
distribution problem, the design team started
with the central plant and the outside air
supply system. By lowering the chilled water
supply temperature at the central plant, colder
supply air was achievable at the floor air-handling
units. Given the same room
temperature conditions, the 45-degree supply
air system required 36 percent less air volume
than a 55-degree system. Reducing the air
volume meant smaller air handling units,
lower fan horsepower, smaller room
requirements and smaller ductwork.
Preconditioning the outside air — rather than
introducing warm moist outside air to each of
the floor air handling units — resulted in the
typical floor coils effectively running dry. Dry
coils have significantly lower air pressure
drop characteristics as compared to coils
covered with condensation. Reducing the
pressure drop meant lower fan horsepower
and less noise. Minimizing the amount of
condensation within the air-handling units
also minimized the chances for
microbiological growth, thereby improving
indoor air quality.
There was a cost premium for the water
chilling units and the addition of a cooling coil
section at the outside air fans, but this cost
premium was more than offset by the cost
savings provided by smaller floor air handling
units, smaller piping systems, smaller
pumping systems, smaller fan horsepower,
smaller ductwork, less sound attenuation,
reduction in electrical service, smaller
equipment rooms and reduced insulation.
New thinking
Conventional wisdom has generally shown it
is necessary to spend more in upfront cost to
achieve higher efficiency, lower operating
costs and superior air conditioning systems.
However, it’s clear that the systematic design
approach combined with the basic
fundamentals of HVAC system design will
generally cut both overall first cost and
operating costs.
Optimizing the advantages of low-temperature
chilled water systems will trim overall first
cost compared with equivalent water-cooled,
self-contained packaged systems, especially if
the effects on the electrical power distribution
are included in the analysis. The cost premium
paid for chillers that have a low supply water
temperature combined with a higher
differential temperature will usually be offset
by the cost saving features in other areas.
Owners, contractors and designers willing to
invest a minimal amount of additional time.
and analysis in the early stages of a project to
pursue this approach will most likely be
rewarded many times over. For the approach
to be successful, contractors must be willing
to move beyond traditional market approaches
and outdated square foot cost models that do
not accurately reflect the materials shown on
the drawings. And beyond the costs involved,
everyone benefits from an overall reduction in
the amount of materials used. By using less
energy, smaller ductwork, smaller piping
systems and smaller components that
comprise systems, buildings use fewer natural
resources and have less overall impact on the
environment.
Russell R. James, PE, is president of TOLK
Inc., an engineering firm in Fairfax, Va
First published April, 2003