Replacing a chiller plant is often one of the largest end-
of-useful-life expenditures facing facility executives.
Although there are many factors to consider while
determining when to replace an aging chiller plant,using
a life-cycle analysis as a decision-making tool allows
facility executives to cover all bases.
A life-cycle analysis considers the four components of
owning and operating costs,including annual utility costs,
maintenance costs,replacement costs and remaining
useful life.All costs are adjusted based on the time value
of money to allow equivalent comparisons.With this
method,all potential system types can be evaluated and
compared to determine the most cost-effective alternative.
Despite the traditional emphasis on minimizing the installed cost of a plant,the most significant expenditure
over the life of the plant is typically the annual operating
costs.For example,consider a plant that has an installed
cost of $500,000,an annual operating cost of $100,000
per year,and a maintenance cost of $20,000 per year.
Assuming a useful life of 20 years,the present value of
the installed cost is $500,000,the operating cost is 1.3
million and the maintenance cost is $250,000.Therefore,
the installed cost accounts for only 25 percent of the total
expenditures over the life of the system.This relationship
should be kept in mind when evaluating alternative
systems.
As that previous example points out,operating costs are
the most significant expenditure over time.Higher first
costs that provide improved efficiency can often be
justified over the life of the system.But there are many
pitfalls that can undermine the decision-making process.
Experience shows that deciding to install the most efficient equipment is always a good idea.But installing
efficient equipment does not automatically assure that a
plant will operate efficiently.Many plants with a low
installed kilowatt per ton operate at a much lower efficiency than older or less efficient plants.The two main
factors that significantly impact chiller plant operating
costs are building load profile and chiller sequencing
strategies.In both cases,plant efficiency is determined
largely by the part-load efficiency of the chillers.
The first tep in evaluating the chiller plant is to develop
the plant load profile.The easiest way to accomplish this
is by using the trending function of the plant ’s energy
management system.Data collected from a chiller plant
should include the entering and leaving water temperature for both the chiller and the condenser,chiller amps,
and status information on chilled water pumps,condenser
water pumps and cooling tower fans.This information
should be collected hourly and can be used to calculate a
part-load performance curve for the chiller and the plant.
As data is gathered and evaluated during the operating
season,a very accurate plant load profile can be generated.
Larger plants with multiple chillers offer a better opportunity to operate the chillers closer to design capacity.
However,it is not an easy task to properly sequence
multiple chillers.Most of the owners of large chiller plants
prefer to sequence chillers manually.Much of the reasoning for this decision is the comfort level from knowing
one of the operators is verifying the operation of the
chillers with “hands-on ”control.Most competent operators are very good at determining when chillers should be
brought online,based on load conditions.However,much
of the low-end part-load operation in a large plant occurs
after a high-load day,when the plant load drifts down
from the peak.Often,multiple chillers may be left idling
for several hours before being taken offline.The ability
to aggressively take chillers offline will have a larger
impact on plant efficiency than the decisions to bring the
chillers on-line.
Both of these factors can have a larger impact on
operating efficiency than the initial design efficiency of a
machine.When considering a chiller plant upgrade,be
sure that the plant has a direct digital control (DDC)
system and a viable sequence of operation before spending additional dollars on a lower kilowatt per ton machine.
In all cases,the control system should have the ability to
monitor,control and verify plant operation.The feedback
from the plant energy management system should be
used to continuously fine tune the operation of the plant.
Relying on operators for average plant load or chiller
sequencing information might result in missed opportunities to significantly improve system operation.
Another factor to consider is the maintenance and repair
cost for chillers.Scheduled maintenance costs for chillers of similar type and size are usually consistent.However,new machines will have lower unscheduled repair
costs than older machines.The historical repair data for
an existing machine can be summarized and included in
the analysis.It is important to review manufacturer
recommendations for the required frequency of component overhauls,especially when comparing different
machine types,such as turbine-driven or centrifugal.An
overhaul can be a significant expenditure and may be
required frequently depending on hours of use.These
expenditures should be identified and included as part of
the life-cycle analysis.Getting a full maintenance service
contract price during the budgeting process,including
required overhauls,is a good way to get a realistic
estimate of these costs on an annualized basis.
The most difficult task in a life-cycle analysis is determining system useful life.ASHRAE committees have conducted numerous studies and surveys performed in an
effort to quantify this information,either through detailed
life studies of individual components or by anecdotal
evidence gathered through operator surveys.Both methods have severe drawbacks in attempting to use the
conclusions to make assumptions about the useful life of
any given system.
Many factors can come into play when determining when
an existing system has reached the end of its useful life.
Some relate to the component itself.Others relate to its
specific application.For example,there are currently
many chillers operating on CFC-based refrigerants.The
manufacture of these refrigerants were legislated out of
existence in the mid 1990s,so that replacement refrigerant would be available only from existing stock.Many
plant operators chose to retrofit or replace their chillers
prior to the phase-out date to assure uninterrupted operations.In hospitals and other critical applications,the
reliability of the equipment is paramount,and decisions
are routinely made to minimize the risk of potential
failure.In these cases,immediate replacement was likely
necessary.Other chiller operators made plans to replace
or retrofit once CFC refrigerants became scarce.In
discussions with plant operators in the mid 1990s,no one
expected their chillers to be operating on CFC-based
refrigerants in 2002.However,with an increased emphasis on leak detection and control,adequate supplies of
refrigerant are still available today and probably will be
for the forseeable future.
So how does an operator address useful life in the
analysis?Unfortunately,there is no universal truth applicable to all situations.However,there are factors that
can minimize its impact.When performing a comparison
between alternative systems,estimates of useful life
must be made for each system type.Fortunately,the
nature of the life-cycle analysis makes the difference
between a system with a 20-year useful life and one with
a 30-year useful life insignificant in terms of present
value.
However,this is not necessarily true in determining
whether to replace an existing plant.In the absence of
factors that necessitate a system replacement,an existing chiller plant could continue to be operated indefinitely.
Indeed,there are a number of chiller plants with equipment installed in the early 1960s that are continue functioning adequately for their specific application.The life-
cycle analysis is the best tool to determine if the system
should be replaced from a financial tandpoint.Beyond
that,it is the responsibility of the facility executive to
decide what level of reliability and risk they are willing to
accept in the operation of their plants.
Boosting Part-load Chiller Efficiency
Part-load operation can significantly affect the operating
efficiency of a chiller.In this example,a machine with a
design efficiency of .5 kw per ton can operate at 1.2 kw
per ton or higher during periods of part-load operation.
The goal in operating the plant is to operate the chillers as
close to design capacity as can be achieved.In the case
of a plant with a single chiller,or two chillers with full
redundancy,the chiller part-load profile is the same as the
plant part-load profile.If you find your load profile is the
typical bell curve centered around 50%load,you may
want to consider installing two smaller chillers to improve
part-load performance.Another alternative may be to
consider a chiller equipped with a variable speed drive,
which is much more efficient under part-load operation.
Joseph J.Watson is a senior project engineer for E3
Designs.He has more than 25 years in the HVAC
industry and recently served as the chairman of the
ASHRAE technical committee on Building Owning
and Operating Costs .
First published February 2002